The construction project is in full swing! Please continue using the back entrance to reach the church and our offices.

Right now the crew is digging trenches outside, which is forcing the temporary closing of the exit driveway.

Third Level

 

See construction photos by Paul Topalian

 

Things are moving along as planned. The Pearson room has a temporary kitchen set up for the use of the congregation’s needs. All plumbing, electrical and drywall has been finished in this space. A crew has been working to get the stage closets back in use. The kitchen has been rough plumbed and most of the electrical work has been done. The garth/courtyard windows have been ordered should be installed by the end of the year. A lot of demolition has been done with much more to come.  Electrical conduit was installed outside and has been run from the street to the church for the new electrical service. A lot of progress has been made and we will continue to work with contractors to execute the plan.