Building Update regarding construction progress.

Below are some of the major accomplishments achieved thus far. The progress is going according to schedule and all parties are content at this point.

Electric – Change over kitchen panel

EBU – emergency lighting done throughout building

Lights in CE wing

Panel installed in new electrical room

New electrical service to Pearson panel

Change over to main panel in new electrical room

Set transformer pad for new electrical service

Conduit installed underground from the street to the building

Plumbing – Rough in kitchen – gas and water lines, grease trap installed

Kitrchen FloorPhotos of Kitchen Floor by Paul Topalian

Removing kitchen floor

The New Kitchen Floor New Kitchen Floor

Pella windows installed at the courtyard

Temporary shoring to support the shaft

Insulation of 3rd floor and kitchen

Marvin window installed on third floor

Trenches in kitchen filled with concrete

Demo of elevator shaft

 Breaking up original foundation wall. The staff wore ear plugs next door

Drilling the floor near the front entrance (closed off area).

Kim's Former Office

Kim Gladstone’s old office.

Stay tuned for upcoming progress!